KUZEYSTAR

Start Date: 01.05.2018
Finish Date: 15.08.2018
Project Equipments: Two Demag CC2800 - 220 ton – 200 tonnes mobile cranes
Project Details:  2 gantry cranes in Altıntaş shipyard in Yalova Altınova Shipyard will be demounted by 2 Demag CC2800 cranes. Afterwards, one of them (small one) will be transported with 3xPPU and 18 axle SPMT and barge (provided by customer) to Kuzey Star Yalova shipyard. The other crane that is disassembled (large one) will be transported to Tuzla with the same SPMT and Barge. Then the disassembled gantry crane from Tuzla will be assembled by the same crawler cranes. Then back to Yalova Shipyard, small gantry crane will be assembled, and operation will be completed.