Start Date: May 2025

End Date: June 2025

Equipment Used in the Project: 2,200-ton SANY SCE22000A Crawler Crane

Project Description: As part of the Abu Dhabi Ramhan Island Bridge project, the lifting operation of 24 girders, each weighing 95 tons, was successfully completed.

Among the alternatives presented to the client, the 2,200-ton capacity crawler crane was selected as a more efficient and cost-effective solution compared to using a barge, completely eliminating the need for marine equipment.

Our proposed approach met all technical and safety requirements while significantly reducing both overall costs and logistical complexity.