ABU DHABI HABSHAN-5 GAS POWER PLANT PROJECT

Start Date: December 2025
End Date: February 2026
Equipment Used in the Project: 64-axle SCHEUERLE SPMT, 60-axle hydraulic trailer 

Project Description: As part of the PE 109 CRI Project – Habshan 5, carried out by Petrofac Emirates LLC in Abu Dhabi, United Arab Emirates, 1 unit of CO₂ Stripper (50.7 m length, 10.5 m width, 10.6 m height, and 601 tons in weight) and 4 units of CO₂ Absorbers were safely transported over a distance of 130 km.

The transportation operation was executed using a 64-axle SCHEUERLE SPMT and a 60-axle hydraulic trailer. During the operation, the convoy progressed along the E11 highway and successfully crossed the Etihad Railway line in the Tarif region.